[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119605":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119605,789,1,"单选题","初步评审中发现投标报价的单价与数量的乘积之和与所报的总价不一致时，应( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","以总价为准",false,{"key":16,"text":17,"correct":14},"B","以大写为准",{"key":19,"text":20,"correct":21},"C","以单价为准，并应由投标人代表签字确认",true,{"key":23,"text":24,"correct":14},"D","以单价为准，无需由投标人代表签字确认","2021\u002F2020教材P229页 “大小写不一致的以大为准，单价与数量的乘积之和与所报的总价不一致的应以单价为准；标书正本和副本不一致的，则以正本为准。这些修改一般应由投标人代表签字确认。”",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]