[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119596":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119596,789,1,"单选题","在施工总承包管理模式下，施工总进度计划的设计、施工、供货等分包单位之间的管理与组织协调应由（）负责。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理工程师",false,{"key":16,"text":17,"correct":14},"B","业主",{"key":19,"text":20,"correct":14},"C","施工总承包单位",{"key":22,"text":23,"correct":24},"D","施工总承包管理单位",true,"2021\u002F2020教材P226页 由施工总承包单位负责对所有分包单位的管理及组织协调，大大减轻了业主的工作。这是施工总承包管理模式的基本出发点。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]