[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119593":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119593,789,1,"单选题","在施工总承包管理模式下，项目总进度计划的编制、控制和协调，以及设计、施工、供货之间的进度计划协调由()负责。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理工程师",false,{"key":16,"text":17,"correct":14},"B","施工总承包单位",{"key":19,"text":20,"correct":21},"C","业主",true,{"key":23,"text":24,"correct":14},"D","施工总承包管理单位","2021\u002F2020教材P226页 施工总进度计划的编制、控制和协调由施工总承包管理单位负责，而项目总进度计划的编制、控制和协调，以及设计、施工、供货之间的进度计划协调由业主负责。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]