[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119590":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119590,789,1,"单选题","下列关于施工总承包管理模式的特点的说明错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对质量控制有利",false,{"key":16,"text":17,"correct":18},"B","开工日期较迟，建设周期势必较长",true,{"key":20,"text":21,"correct":14},"C","业主对组织与协调的工作大大减轻",{"key":23,"text":24,"correct":14},"D","招标及合同管理的工作量较大，对业主不利","2021\u002F2020教材P226页 对施工总承包管理单位的招标不依赖于完整的施工图设计，可以提前到初步设计阶段进行。而对分包单位的招标依据该部分工程的施工图，与施工总承包模式相比也可以提前，从而可以提前开工，缩短建设周期。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]