[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119586":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119586,789,1,"单选题","某工程采用施工总承包管理模式，施工总承包管理单位认为业主选定的某个分包人确实没有能力完成分包任务，而业主又执意不肯更换该分包人，则()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工总承包管理单位应认可该分包合同",false,{"key":16,"text":17,"correct":14},"B","施工总承包管理单位应认可该分包合同，但不承担对该分包人所负责工程的管理责任",{"key":19,"text":20,"correct":14},"C","施工总承包管理单位可以拒绝认可该分包合同，但应承担对该分包人所负责工程的管理责任",{"key":22,"text":23,"correct":24},"D","施工总承包管理单位可以拒绝认可该分包合同，并且不承担对该分包人所负责工程的管理责任",true,"2021\u002F2020教材P225页 “如果施工总承包管理单位认为业主选定的某个分包人确实没有能力完成分包任务，而业主执意不肯更换该分包人，施工总承包管理单位也可以拒绝认可该分包合同，并且不承担该分包人所负责工程的管理责任”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]