[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119585":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119585,789,1,"单选题","某工程项目采用施工总承包管理模式，如施工总承包管理单位想承接该工程部分具体工程的施工任务，则其可通过()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理单位委托取得任务",false,{"key":16,"text":17,"correct":18},"B","投标竞争取得任务",true,{"key":20,"text":21,"correct":14},"C","施工总承包人委托取得任务",{"key":23,"text":24,"correct":14},"D","自行分配取得任务","2021\u002F2020教材P224页 三、施工总承包管理模式（一）施工总承包管理的含义一般情况下，施工总承包管理单位不参与具体工程的施工，而具体工程的施工需要再进行分包单位的招标与发包，把具体工程的施工任务分包给分包商来完成。但有时也存在另一种情况，即施工总承包管理单位也想承担部分具体工程的施工，这时它也可以参加这一部分工程施工的投标，通过竞争取得任务。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]