[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119578":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119578,789,1,"单选题","施工总承包模式的一般工作程序为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工图设计完成→施工总承包的招投标→施工→竣工验收",true,{"key":16,"text":17,"correct":18},"B","施工图设计完成→施工→施工总承包的招投标→竣工验收",false,{"key":20,"text":21,"correct":18},"C","施工总承包的招投标→施工图设计完成→施工→竣工验收",{"key":23,"text":24,"correct":18},"D","施工总承包的招投标→施工→施工图设计完成→竣工验收","2021\u002F2020教材P223页 施工总承包一般工序为：施工图完成设计-施工总承包的招投标-施工-竣工验收",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]