[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119573":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119573,789,1,"单选题","关于施工平行承发包的应用，下列说法错误的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对施工任务的平行发包，发包方不能根据建设项目的结构进行分解发包",true,{"key":16,"text":17,"correct":18},"B","对施工任务的平行发包，发包方可以根据建设项目的结构进行分解发包",false,{"key":20,"text":21,"correct":18},"C","对施工任务的平行发包，发包方可以根据建设项目施工的不同专业系统进行分解发包",{"key":23,"text":24,"correct":18},"D","最后一份合同签订后，业主才知道整个工程的总造价","2021\u002F2020教材P223页 对施工任务的平行发包，发包方可以根据建设项目的结构进行分解发包，也可以根据建设项目施工的不同专业系统进行分解发包。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]