[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119572":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119572,789,1,"单选题","关于施工总承包模式特点的说法，正确的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工总承包单位负责项目总进度计划的编制、控制、协调",false,{"key":16,"text":17,"correct":14},"B","项目质量取决于业主的管理水平和施工总承包单位的技术水平",{"key":19,"text":20,"correct":21},"C","在开工前就有明确的合同价，有利于业主对总造价的早期控制",true,{"key":23,"text":24,"correct":14},"D","业主需负责施工总承包单位和分包单位的管理和组织协调","2021\u002F2020教材P223页 1.费用控制(1)在通过招标选择施T总承包单位时，一般都以施工图设计为投标报价的基础，投标人的投标报价较有依据；(2)在开工前就有较明确的合同价，有利于业主对总造价的早期控制；(3)若在施工过程中发生设计变更，则可能发生索赔。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]