[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119567":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119567,789,1,"单选题","对业主来说，要等最后一份合同签订后才知道整个工程的总造价，对投资的早期控制不利，属于施工平行承发包模式中的()的特点。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","费用控制",true,{"key":16,"text":17,"correct":18},"B","进度控制",false,{"key":20,"text":21,"correct":18},"C","质量控制",{"key":23,"text":24,"correct":18},"D","合同管理","2021\u002F2020教材P222页 对业主来说，要等最后一份合同签订后才知道整个工程的总造价，对投资的早期控制不利。进度控制，工程总进度计划和控制由业主负责，由不同单位承包的各部分工程之间的进度计划及其实施的协调由业主负责（业主直接抓各个施工单位似乎控制力度大，但矛盾集中，业主的管理风险大）质量控制，对某些工作而言，符合质量控制上的他人控制原则，不同分包单位之间能够形成一定的控制和制约机制，对业主的质量控制有利。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]