[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119566":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119566,789,1,"单选题","某开发公司计划建设一幢高档写字楼项目，采用施工总承包管理模式，并在未完成施工图设计的情况下采用“费率招标”方式进行招标。这种方式对业主在费用控制方面的影响是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","在开工前就有较明确的合同价，有利于业主对总造价的早期控制",false,{"key":16,"text":17,"correct":18},"B","在开工前合同价格不明确，不利于业主对总造价的早期控制",true,{"key":20,"text":21,"correct":14},"C","费用控制的好坏在很大程度上取决于施工总承包单位的选择",{"key":23,"text":24,"correct":14},"D","在施工过程中发生设计变更，产生索赔的可能性小","2021\u002F2020教材P223页 (二)施工总承包的特点。1.费用控制：（2）在开工前就有较明确的合同价，有利于业主对总造价的早期控制;而施工总承包管理模式则是合同价格不明确，因为图纸没有设计完成。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]