[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119563,789,1,"单选题","施工平行承发包模式适用于()的情况。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","将工程分解发包，业主无需过多地照顾各种关系",false,{"key":16,"text":17,"correct":14},"B","项目规模不大",{"key":19,"text":20,"correct":14},"C","业主缺乏足够的经验和能力应对多家施工单位",{"key":22,"text":23,"correct":24},"D","由于项目建设的时间要求紧迫，业主急于开工，来不及等所有的施工图全部出齐，只有边设计、边施工",true,"2021\u002F2020教材P222页 (三）施工平行发包的应用： (1)当项目规模很大，不可能选择一个施工单位进行施工总承包或施工总承包管理，也没有一个施工单位能够进行施工总承包或施工总承包管理； (2）由于项目建设的时间要求紧迫，业主急于开工，来不及等所有的施工图全部出齐，只有边设计、边施工； (3）业主有足够的经验和能力应对多家施工单位； (4）将工程分解发包，业主可以尽可能多地照顾各种关系……",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]