[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119555":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119555,789,1,"单选题","实行施工平行承发包对建设工程项目进度控制的影响表现为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主要负责所有施工承包合同的招标、合同谈判、签约，招标及合同管理工作量大，对业主不利",false,{"key":16,"text":17,"correct":14},"B","每一部分工程的施工，发包人都可以通过招标选择最好的施工单位承包，对降低工程造价有利",{"key":19,"text":20,"correct":21},"C","由于要进行多次招标，业主用于招标的时间较多",true,{"key":23,"text":24,"correct":14},"D","业主直接控制所有工程的发包，确定所有工程的承包商","2021\u002F2020教材P222页 2.进度控制（2）由于要进行多次招标，业主用于招标的时间较多。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]