[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119554":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119554,789,1,"单选题","某建设工程包括土建、安装、装饰装修等若干单位工程，现业主将土建工程发包给甲施工单位，安装工程发包给乙施工单位，装饰装修工程发包给丙施工单位。对业主来说，这样的发包方式在费用控制与进度控制方面的特点是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对投资的早期控制不利，且不利于缩短建设周期",false,{"key":16,"text":17,"correct":18},"B","对投资的早期控制不利，但有利于缩短建设周期",true,{"key":20,"text":21,"correct":14},"C","对投资的早期控制较为有利，且不利于缩短建设周期",{"key":23,"text":24,"correct":14},"D","对投资的早期控制较为有利，也有利于缩短建设周期","2021\u002F2020教材P222页 1.费用控制（3）对于业主来说，要等到最后一份合同签订后才知道整个工程的总造价，对投资的早期控制不利。2.进度控制（1）某一部分施工图完成后，即可开始这部分工程的招标，开工日期提前，可以边设计边施工，缩短建设周期。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]