[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119539":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119539,789,1,"单选题","根据施工现场环境保护的要求，凡在人口稠密区进行强噪声作业时，须严格控制作业时间。一般情况下，停止强噪声作业的时间是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","晚9点到次日早4点之间",false,{"key":16,"text":17,"correct":18},"B","晚10点到次日早6点之间",true,{"key":20,"text":21,"correct":14},"C","晚11点到次日早4点之间",{"key":23,"text":24,"correct":14},"D","晚10点到次日早5点之间","2021\u002F2020教材P219页 (2)在人口密集区进行较强噪声施工时，须严格控制作业时间，一般避开晚10时到次日早6时的作业.",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]