[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119505":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119505,789,1,"单选题","下列分部分项工程的专项施工方案中，需要组织专家进行论证、审查的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","拆除、爆破工程",false,{"key":16,"text":17,"correct":14},"B","脚手架工程",{"key":19,"text":20,"correct":21},"C","地下暗挖工程",true,{"key":23,"text":24,"correct":14},"D","起重吊装工程","2021\u002F2020教材P199页 7.专项施工方案专家论证制度：对前款所列工程中涉及深基坑、地下暗挖工程、高大模板工程的专项施工方案，施工单位还应当组织专家进行论证、审查。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]