[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119504,789,1,"单选题","下列关于安全隐患的处理程序，排序正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","整改-登记-复查-销案",false,{"key":16,"text":17,"correct":14},"B","登记-复查-整改-销案",{"key":19,"text":20,"correct":21},"C","登记-整改-复查-销案",true,{"key":23,"text":24,"correct":14},"D","整改-登记-销案-复查","2021\u002F2020教材P200页 安全隐患的处理程序。对查出的安全隐患，不能立即整改的，要制定整改计划，定人、定措施、定经费、定完成日期；在未消除安全隐患前，必须采取可靠的防范措施，如有危及人身安全的紧急险情，应立即停工；并按照“登记-整改-复查-销案”的程序处理安全隐患。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]