[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119418":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119418,789,1,"单选题","施工项目一旦发生安全事故,必须实施“四不放过”的原则,其内容不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","事故原因没有査清不放过",false,{"key":16,"text":17,"correct":18},"B","事故损失未挽回不放过",true,{"key":20,"text":21,"correct":14},"C","责任人员没有受到处理不放过",{"key":23,"text":24,"correct":14},"D","职工群众没有受到教育不放过","2021\u002F2020教材P210页 “四不放过”的原则包括:事故原因没有査清不放过、责任人员没有受到处理不放过、职工群众没有受到教育不放过、防范措施没有落实不放过。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]