[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119372":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119372,789,1,"单选题","根据风险评价所得出的不同风险源和风险量大小（风险水平），选择不同的控制策略。当不需要另外的控制措施，而应考虑投资效果更佳的解决方案或不增加额外成本的改进措施，需要监视来确保控制措施得以维持时，则风险水平属于()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","可忽略的",false,{"key":16,"text":17,"correct":18},"B","可容许的",true,{"key":20,"text":21,"correct":14},"C","中度的",{"key":23,"text":24,"correct":14},"D","重大的","2021\u002F2020教材P204页 2Z105022-2中内容，当风险为可容许的，不需要另外的控制措施，应考虑投资效果更佳的解决方案或不增加额外成本的改进措施，需要监视来确保控制措施得以维持。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]