[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119371":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119371,789,1,"单选题","制定的风险控制措施计划应该在实施前予以评审，评审的内容不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预防性测定指标是否符合监视控制措施计划的要求",true,{"key":16,"text":17,"correct":18},"B","更改的控制措施是否使风险降至可允许的水平",false,{"key":20,"text":21,"correct":18},"C","是否产生了新的危险源",{"key":23,"text":24,"correct":18},"D","是否已选定了成本效益最佳的解决方案","2021\u002F2020教材P204页 风险控制措施计划在实施前宜进行评审。评审主要包括以下内容：(1)更改的措施是否使风险降低至可允许水平；(2)是否产生新的危险源；(3)是否已选定了成本效益最佳的解决方案；(4)更改的预防措施是否能得以全面落实。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]