[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119370":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119370,789,1,"单选题","根据不同风险水平的风险控制措施计划表,对于“中度的”风险,宜采取的措施是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","直至风险降低后才能开始工作,当风险涉及正在进行中的工作时,应采取应急计划",false,{"key":16,"text":17,"correct":14},"B","考虑投资效果更佳的解决方案或不增加额外成本的改进措施",{"key":19,"text":20,"correct":14},"C","只有当风险已经降低到“可容许的”水平时,才能就开始或继续工作。",{"key":22,"text":23,"correct":24},"D","应努力降低风险,并在规定的时间期限内实施降低风险的措施。",true,"2021\u002F2020教材P204页 对于中度风险,应努力降低风险,但应仔细测定并限定预防成本,并在规定的时间期限内实施降低风险的措施。在中度风险与严重伤害后果相关的场合,必须进一步的评价,以更准确的确定伤害的可能性,以确定是否需要改进控制措施。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]