[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119368":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119368,789,1,"单选题","针对第Ⅳ类风险（重大风险）应该采取的风险控制措施为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","只有当风险已经降低时，才能开始或继续工作。如果无限的资源投入也不能降低风险，就必须禁止工作",false,{"key":16,"text":17,"correct":14},"B","应努力降低风险，但应仔细测定并限定预防成本，并在规定的时间期限内实施降低风险的措施",{"key":19,"text":20,"correct":21},"C","直至风险降低后才能开始工作，为降低风险有时必须配给大量的资源",true,{"key":23,"text":24,"correct":14},"D","应考虑投资效果更佳的解决方案或不增加额外成本的改进措施","2021\u002F2020教材P204页 表2Z105022-2中重大的直至风险降低后才能开始工作。为降低风险有时必须配合给大量的资源。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]