[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119344":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119344,789,1,"单选题","安全技术措施计划编制可以按照“①制定安全技术措施计划评价；②安全技术措施计划的充分性；③工作活动分类；④危险源识别；⑤风险确定；⑥风险评价”的步骤进行。下列选项中，正确的排序是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①②③④⑤⑥",false,{"key":16,"text":17,"correct":14},"B","④⑤⑥②①③",{"key":19,"text":20,"correct":21},"C","③④⑤⑥①②",true,{"key":23,"text":24,"correct":14},"D","④⑤⑥①②③","2021\u002F2020教材P199页 安全技术措施计划编制可以按照“工作活动分类→危险源识别→风险确定→风险评价→制定安全技术措施计划评价→安全技术措施计划的充分性”的步骤进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]