[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119330":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119330,789,1,"单选题","企业进行生产活动时，必须编制安全措施计划，其编写步骤为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","危险源识别→工作活动分类→风险确定→风险评价→制定安全技术措施计划→评价安全技术措施计划的充分性",false,{"key":16,"text":17,"correct":14},"B","工作活动分类→危险源识别→风险确定→风险评价→评价安全技术措施计划的充分性→制定安全技术措施计划",{"key":19,"text":20,"correct":14},"C","危险源识别→工作活动分类→风险确定→风险评价→评价安全技术措施计划的充分性→制定安全技术措施计划",{"key":22,"text":23,"correct":24},"D","工作活动分类→危险源识别→风险确定→风险评价→制定安全技术措施计划→评价安全技术措施计划的充分性",true,"2021\u002F2020教材P199页 安全技术措施计划编制可以按照“工作活动分类→危险源识别→风险确定→风险评价→制定安全技术措施计划评价→安全技术措施计划的充分性”的步骤进行。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]