[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119288":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119288,789,1,"单选题","建设工程施工过程中，对于有毒、有害物质超过国家标准的建筑材料和装修材料，应是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","禁止生产、销售和使用",true,{"key":16,"text":17,"correct":18},"B","经有关部门批准可部分使用",false,{"key":20,"text":21,"correct":18},"C","经设计优化采取防护措施后使用",{"key":23,"text":24,"correct":18},"D","不影响施工人员健康条件下使用","2021\u002F2020教材P191页 建筑材料和装修材料必须符合国家标准。禁止生产、销售和使用有毒、有害物质超过国家标准的建筑材料和装修材料。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]