[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119285":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119285,789,1,"单选题","具有防治污染设施的建设工程项目可投入生产或者使用的条件是，防治污染的设施必须经（）验收合格。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目所在地的建设主管部门",false,{"key":16,"text":17,"correct":14},"B","项目投资人所在地的环境保护行政主管部门",{"key":19,"text":20,"correct":14},"C","审批设计文件的建设主管部门",{"key":22,"text":23,"correct":24},"D","原审批环境影响报告书的环境保护行政主管部门",true,"2021\u002F2020教材P191页 防治污染的设施必须经原审批环境影响报告书的环境保护行政主管部门验收合格后，该建设工程项目方可投入生产或者使用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]