[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119237":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119237,789,1,"单选题","建设单位应将施工、设计、监理和建设单位各方分别签字的质量验收证明在验收后( )内报送工程质量监督机构备案。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","三天",true,{"key":16,"text":17,"correct":18},"B","五天",false,{"key":20,"text":21,"correct":18},"C","七天",{"key":23,"text":24,"correct":18},"D","十天","2021\u002F2020教材P183页 建设单位应将施工、设计、监理和建设单位各方分别签字的质量验收证明在验收后三天内报送工程质量监督机构备案。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]