[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119236":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119236,789,1,"单选题","监督机构对基础和主体结构阶段的施工应安排监督检查的周期是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","每周",false,{"key":16,"text":17,"correct":14},"B","每季度",{"key":19,"text":20,"correct":21},"C","每月",true,{"key":23,"text":24,"correct":14},"D","每天","2021\u002F2020教材P183页 监督机构检查参与工程建设各方的质量行为及质量责任制的履行情况，工程实体质量和质量控制资料的完成情况，其中对基础和主体结构阶段的施工应每月安排监督检查。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]