[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119226":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119226,789,1,"单选题","建设工程质量监督机构进行第一次施工现场监督检查的重点是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工现场准备情况",false,{"key":16,"text":17,"correct":14},"B","检查施工现场计量器具",{"key":19,"text":20,"correct":21},"C","参加建设的各单位的质量行为",true,{"key":23,"text":24,"correct":14},"D","复核项目测量控制定位点","2021\u002F2020教材P183页 在工程项目开工前，监督机构首先在施工现场召开由参与工程建设各方代表参加的监督会议，公布监督方案，提出监督要求，并进行第一次的监督检查工作。检查的重点是参与工程建设各方主体的质量行为。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]