[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119220":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119220,789,1,"单选题","工序施工质量控制属于（ ）质量控制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","事前",false,{"key":16,"text":17,"correct":14},"B","事中",{"key":19,"text":20,"correct":21},"C","事后",true,{"key":23,"text":24,"correct":14},"D","过程","2021\u002F2020教材P167页 2.工序施工效果控制 工序施工质量控制属于事后质量控制。 @##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]