[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119217":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119217,789,1,"单选题","在施工准备阶段，绘制模板配板图属于()的质量控制工作。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计量控制准备",false,{"key":16,"text":17,"correct":14},"B","测量控制准备",{"key":19,"text":20,"correct":21},"C","施工技术准备",true,{"key":23,"text":24,"correct":14},"D","施工平面控制","2021\u002F2020教材P164页 技术准备是指在正式开展施工作业活动前进行的技术准备工作。这类工作内容繁多，主要在室内进行，例如：熟悉施工图纸，进行详细的设计交底和图纸审查；细化施工技术方案和施工人员、机具的配置方案，编制施工作业技术指导书，绘制各种施工详图（如测量放线图、大样图及配筋、配板、配线图表等），进行必要的技术交底和技术培训。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]