[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119203":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119203,789,1,"单选题","对于特殊施工过程的质量控制，应严格按照三级检查制度进行检查控制。在施工中发现质量控制点异常时，正确的处理方式是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","继续施工的同时上报上级主管部门，分析原因并解决",false,{"key":16,"text":17,"correct":18},"B","立即停止施工，召开分析会，查找原因采取对策",true,{"key":20,"text":21,"correct":14},"C","组织专家对施工过程进行现场检测分析",{"key":23,"text":24,"correct":14},"D","停止施工，并等候施工监理的指示","2021\u002F2020教材P170页 为保证质量控制点的目标实现，应严格按照三级检查制度进行检查控制。在施工中发现质量控制点有异常时，应立即停止施工，召开分析会，查找原因采取对策予以解决。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]