[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119202":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119202,789,1,"单选题","在施工质量控制点的控制中，对冷拉钢筋应注意先焊接之后再进行冷拉，这是从（ ）方面加强重点控制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","关键操作",false,{"key":16,"text":17,"correct":14},"B","技术间歇",{"key":19,"text":20,"correct":21},"C","施工顺序",true,{"key":23,"text":24,"correct":14},"D","施工技术参数","2021\u002F2020教材P170页 施工顺序。对于某些工序之间必须严格控制施工的先后顺序，比如对冷拉的钢筋应当先焊接后冷拉，否则会失去冷强。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]