[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119169":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119169,789,1,"单选题","在工程项目开工前，监督机构接受建设单位有关建设工程质量监督的申报手续，并对建设单位提供的有关文件进行审查，审查合格签发有关质量监督文件，建设单位凭工程质量监督文件，向（）申领施工许可证。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量监督机构",false,{"key":16,"text":17,"correct":18},"B","建设行政主管部门",true,{"key":20,"text":21,"correct":14},"C","政府主管部门",{"key":23,"text":24,"correct":14},"D","监督机构负责人","2021\u002F2020教材P183页 在工程项目开工前，监督机构接受建设单位有关建设工程质量监督的申报手续，并对建设单位提供的有关文件进行审查，审查合格签发有关质量监督文件。建设单位凭工程质量监督文件，向建设行政主管部门申领施工许可证。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]