[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119149":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119149,789,1,"单选题","质量管理的PDCA循环中，实施阶段工作内容包括（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定质量目标",false,{"key":16,"text":17,"correct":14},"B","检查计划执行的结果",{"key":19,"text":20,"correct":21},"C","进行计划行动方案的部署和交底",true,{"key":23,"text":24,"correct":14},"D","制定实现质量目标的行动方案","2021\u002F2020教材P159页 实施包含两个环节，即计划行动方案的交底和按计划规定的方法及要求展开的施工作业技术活动。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]