[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119145":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119145,789,1,"单选题","某施工企业承担了某项施工任务，为保证项目目标的实现，项目经理做了以下各项工作，其中属于项目目标事前控制的内容是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","收集项目目标的实际值",false,{"key":16,"text":17,"correct":14},"B","定期进行项目目标的计划值与实际值比较",{"key":19,"text":20,"correct":21},"C","针对影响项目目标的各种因素采取预防措施",true,{"key":23,"text":24,"correct":14},"D","当发现目标偏离时，采取纠偏措施进行纠偏","2021\u002F2020教材P161页 1. 事前质量控制即在正式施工前进行的事前主动质量控制，通过编制施工质 量计划，明确质量目标，制定施工方案，设置质量管理点，落实质量责任，分析可能导致质量目标偏离的各种影响因素，针对这些影响因素制定有效的预防措施，防患于未然。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]