[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119143":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119143,789,1,"单选题","在施工质量控制环节中，事中控制首先是对( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量活动的行为约束",true,{"key":16,"text":17,"correct":18},"B","质量活动过程和结果的监督控制",false,{"key":20,"text":21,"correct":18},"C","制订施工方案的控制",{"key":23,"text":24,"correct":18},"D","质量偏差的纠正和控制","2021\u002F2020教材P161页 选项B不正确，事中控制首先是对质量活动的行为约束，然后是对质量活动过程和结果的监督控制；选项C是事前控制的工作内容；选项D是事后控制的工作内容。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]