[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119136":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119136,789,1,"单选题","施工质量保证体系是按照PDCA循环的原理实施的，根据项目自身可能存在的质量问题、质量通病以及与国家规范规定的质量标准对比的差距提出质量管理目标，属于PDCA循环中的（）环节",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划",true,{"key":16,"text":17,"correct":18},"B","实施",false,{"key":20,"text":21,"correct":18},"C","检查",{"key":23,"text":24,"correct":18},"D","处置","2021\u002F2020教材P158页 计划是质量管理的首要环节，通过计划，确定质量管理的方针、目标，以及实现方 针、目标的措施和行动方案。计划包括质量管理目标和质量保证工作计划。质量管理目标的确定，就是根据项目自身特点，针对可能发生的质量问题 、质量通病，以及与国家规范规定的质量标准的差距，或者用户提出的更新、更高的质量要求。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]