[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119135":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119135,789,1,"单选题","施工质量控制的基本方法PDCA的中文解释为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划—实施—对比—处理",false,{"key":16,"text":17,"correct":18},"B","计划—实施—检查—处理",true,{"key":20,"text":21,"correct":14},"C","计划—实施—对比—纠偏",{"key":23,"text":24,"correct":14},"D","计划—实施—检查—纠偏","2021\u002F2020教材P158页 施工质量保证体系的运行，应以质量计划位主线，以过程管理为重心，按照PDCA循环原理展开，即计划、实施、检查和处理的步骤展开。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]