[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119134":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119134,789,1,"单选题","做好( )阶段的质量控制是确保施工质量的先决条件。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","设计",false,{"key":16,"text":17,"correct":14},"B","决策",{"key":19,"text":20,"correct":21},"C","施工准备",true,{"key":23,"text":24,"correct":14},"D","施工","2021\u002F2020教材P158页 施工准备阶段的质量控制：施工准备是为整个工程施工创造条件，准备工作的好坏，不仅直接关系到工程建设能否高速、优质地完成，而且也决定了能否对工程质量事故起到一定的预防、控制作用。因此，做好施工准备阶段的质量控制是确保施工质量的首要工作。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]