[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119112":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119112,789,1,"单选题","某工程第三层混凝土现浇楼面的平整偏差达到10mm，其后续作业为找平层和面层的施工，这时应该()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","加固处理",false,{"key":16,"text":17,"correct":14},"B","修补处理",{"key":19,"text":20,"correct":21},"C","不作处理",true,{"key":23,"text":24,"correct":14},"D","限制使用","2021\u002F2020教材P181页 （2）后道工序可以弥补的质量缺陷。例如，混凝土结构表面的轻微麻面，可通过后续的抹灰、刮涂、喷涂等弥补，也可不做处理。再比如，混凝土现浇楼面的平整度偏差达到10mm，但由于后续垫层和面层的施工可以弥补，所以也可不作处理。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]