[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119062":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119062,789,1,"单选题","根据《质量管理体系基础和术语》GB\u002FT 19000-2008的规定，凡工程产品没有满足质量要求，就称为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","质量不合格",true,{"key":16,"text":17,"correct":18},"B","质量缺陷",false,{"key":20,"text":21,"correct":18},"C","质量问题",{"key":23,"text":24,"correct":18},"D","质量事故","2021\u002F2020教材P174页 工程质量事故的概念。1. 质量不合格根据我国《质量管理体系基础和术语》GB\u002FT 19000—2016 的术语解释，凡工程产品未满足质量要求，就称之为质量不合格；与预期或规定用途有关的不合格，称为质量缺陷。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]