[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119042":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119042,789,1,"单选题","工程竣工验收()前，建设单位应将验收的时间、地点及验收组名单书面通知当地工程质量监督站",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3个工作日",false,{"key":16,"text":17,"correct":18},"B","7个工作日",true,{"key":20,"text":21,"correct":14},"C","5个工作日",{"key":23,"text":24,"correct":14},"D","48小时","2021\u002F2020教材P174页 (3)建设单位应当在工程竣工验收7个工作日前将验收的时间、地点及验收组 名单书面通知负责监督该工程的工程质量监督机构。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]