[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119040":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119040,789,1,"单选题","建设单位应当在工程竣工验收()前将验收的时间、地点以及验收组名单书面通知工程质量监督机构。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3日",false,{"key":16,"text":17,"correct":14},"B","7日",{"key":19,"text":20,"correct":21},"C","7个工作日",true,{"key":23,"text":24,"correct":14},"D","3个工作日","2021\u002F2020教材P174页 竣工验收由建设单位组织，验收组由建设、勘察、设计、施工、监理和其他有关方面的专家组成，验收组可下设若干个专业组。建设单位应在工程竣工验收7个工作日前将验收的时间、地点以及验收组名单书面通知当地工程 质量监督站 。注意，不是7天，是7个工作日。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]