[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119037":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119037,789,1,"单选题","某混凝土结构工程施工完成2个月后，发现较深且宽度为15mm的裂缝，经法定的检测单位鉴定，该裂缝已危及到结构构件的承载力，对此质量问题，恰当的处理方式是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","修补处理",false,{"key":16,"text":17,"correct":18},"B","加固处理",true,{"key":20,"text":21,"correct":14},"C","返工处理",{"key":23,"text":24,"correct":14},"D","不作处理","2021\u002F2020教材P173页 若经法定检测单位检测鉴定以后认为达不到规范标准的相应要求，即不能满足 最低限度的安全储备和使用功能，则必须按一定的技术方案进行加固处理，使之能保证其满足安全使用的基本要求。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]