[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119033":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119033,789,1,"单选题","某工程进行检验批验收付时，发现某框架梁截面尺寸与原设计图纸尺寸不符，但经原设计单位核算，仍能满足结构安全性及使用性要求。则该检验批()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","应重新施工",false,{"key":16,"text":17,"correct":14},"B","应经施工单位和业主协商确定是否予以验收，其经济责任由业主承担",{"key":19,"text":20,"correct":21},"C","可直接予以验收",true,{"key":23,"text":24,"correct":14},"D","必须进行加固处理后重新组织验收","2021\u002F2020教材P172页 第三种情况，如经检测鉴定达不到设计要求时，但经原设计单位核算仍能满足结构安全和使用功能的情况，该检验批可予以验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]