[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119031":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119031,789,1,"单选题","在工程验收过程中，发现个别检验批试块强度不满足要求，但是请具有资质的法定检测单位检测鉴定后，鉴定结果能够达到设计要求。这种情况下应( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","认为通过验收",true,{"key":16,"text":17,"correct":18},"B","不能通过验收",false,{"key":20,"text":21,"correct":18},"C","由建设单位决定是否通过验收",{"key":23,"text":24,"correct":18},"D","需要返工","2021\u002F2020教材P172页 第二种情况，是指个别检验批发现试块强度等不满足要求等问题，难以确定可 否验收时，应请具有法定资质的检测单位检测鉴定。当鉴定结果能够达到设计要求时，该检验批 仍应认为通过验收。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]