[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119019":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119019,789,1,"单选题","关于分部工程质量验收合格应符合的规定，下列选项中不正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","所含分项工程的质量均验收合格",false,{"key":16,"text":17,"correct":14},"B","质量控制资料完整",{"key":19,"text":20,"correct":21},"C","工程施工符合设计文件的要求",true,{"key":23,"text":24,"correct":14},"D","观感质量验收符合要求","2021\u002F2020教材P171页 分部工程质量验收合格应符合下列规定：①分部工程所含分项工程的质量均应验收合格；②质量控制资料应完整；③地基与基础、主体结构和设备安装等分部工程有关安全及功能的验收和抽样检测结果符合有关规定；④观感质量验收应符合要求。C项，工程施工符合设计文件的要求为施工项目竣工验收的要求。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]