[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119015":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119015,789,1,"单选题","下列施工质量控制点中，从关键操作与施工方法的角度进行重点控制的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","液压滑模施工时支承杆稳定控制",true,{"key":16,"text":17,"correct":18},"B","混凝土的外加剂掺量控制",false,{"key":20,"text":21,"correct":18},"C","抹灰层干燥后才能刷浆",{"key":23,"text":24,"correct":18},"D","砌体的砂浆饱满度控制","2021\u002F2020教材P170页 （3）施工方法与关键操作： 如大模板施工中模板的稳定组装问题、液压滑模施工时支承杆稳定问题、升板法施工中提升差的控制等。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]