[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119011":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119011,789,1,"单选题","下述工作中，属于特殊过程质量控制工作内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","选择质量控制点并实施控制",true,{"key":16,"text":17,"correct":18},"B","建筑物施工过程中的沉降观测",false,{"key":20,"text":21,"correct":18},"C","对施工中各种投入要素质量进行控制",{"key":23,"text":24,"correct":18},"D","对可能引起工程变更的因素和条件进行管理和控制","2021\u002F2020教材P169页 对在项目质量计划中界定的特殊过程，应设置工序质量控制点，抓住影响工序施工质量的主要因素进行强化控制。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]